The Deelux week-by-week timeline
Every Deelux kitchen follows the same timeline. These are our real figures, not marketing numbers — you’ll find the same on our lead times page.
Weeks 0 to 4 — Discovery and design (before the clock starts)
- Week 0 — Discovery and showroom visit. Free, no deposit taken.
- Week 1 — Free home survey and laser measurement by a Deelux designer.
- Weeks 2–3 — First photoreal 3D visuals presented.
- Weeks 3–4 — Design revisions and a final quote.
Week 4 — Signed order. This is when the 8–12 week clock starts.
A deposit is paid on sign-off and manufacture begins immediately. The balance is paid on delivery and installation.
Weeks 5 to 10 — Manufacture in Winsford
Your cabinets are built at our factory in Winsford, twenty miles from Chester. Every carcass is personally built by Andy Jervis, our director and chief fabricator. Doors, worktops and accessories are prepared in parallel.
Week 10 — Delivery and installation begins
Our own in-house fitting team — never sub-contracted — arrives at your Chester home. A standard installation typically runs:
- Day 1 — Strip-out of the old kitchen (if we haven’t done it in a previous visit)
- Days 2–5 — Cabinet fit, first fix of plumbing and electrics
- Days 6–8 — Worktop templating (solid stone and quartz need a separate templating visit before installation)
- Days 9–12 — Worktop fit, appliances, splashbacks, plastering touch-ups, tiling
- Days 13–15 — Final snag walk, decoration, sign-off
Weeks 10 to 12 — Snagging and final handover
Any minor adjustments, paint touch-ups or appliance tweaks are handled before we hand over. You don’t pay the final balance until you’re happy the kitchen is finished.